Winslow Constructors’ Bendigo region team recently completed the first stage of Invicta Industrial Estate, the regional Victorian city’s first greenfield industrial precinct of its scale in eight years.

Work on the first stage, a 35-lot industrial subdivision, involved the installation of three bridge culvert structures.

The development features more than 20,900m² of pavement, over 100,000m³ of cut-and-fill placement, and more than 5000 tonnes of asphalt.

WC Invicta 2 1200x627

Additionally, the project includes 1500m² of rock beaching and 1600m of drainage with depths reaching 3m.

The project includes 2500m sewer infrastructure, with depths of up to 4m, along with a new sewer pump station.

Concrete sleeper retaining walls extend 360m, with heights ranging from 1m to 3m, and native landscaping, performed by Native Space, will complete the site.

A challenge has been the active swale running through the centre of the site, complicating construction, however, the team managed any difficulties, ensuring the delivery of Stage 1 with work beginning soon on Stage 2.

The 23ha estate is a collaborative effort with developer Hickory Group.